Loading ...
Loading ...
Loading ...
![](https://manualsfile.com/fullContents/37153897-evmagu23x-new/bg87.png)
Powering down/up applications (examples)
Servicing the Network Management Module – 135
4.3.2 Powering down non-priority equipment first
4.3.2.1 Target
Powering down non-priority equipment first (immediately) and keep battery power for critical equipment.
Powering down critical equipment 3min before the end of backup time.
4.3.2.2 Step 1: Installation setup
4.3.2.2.1 Objective
Use load segmentation provided by the UPS to independently control the power supply of each IT equipment categories
(Applications, Database servers, Storage).
Load segmentation also allows IT equipment to restart sequentially on utility recovery(
Restart sequentially the IT equipment on
utility recovery).
Loading ...
Loading ...
Loading ...