Connect wiring — general information
Part number 550-142-330/0421
26
SGO
OIL-FIRED NATURAL DRAFT STEAM BOILER — SERIES 4 — Boiler Manual
SERVICE฀TECHNICIAN฀ONLY฀—฀read฀and฀follow฀completely.
General wiring requirements
ELECTRIC SHOCK HAZARD – Can cause severe
personal injury or death if power source, includ-
ing service switch on boiler, is not disconnected
before installing or servicing.
Installations must follow these codes:
•฀National Electrical Code, ANSI/NFPA 70, – latest edi-
tion and any additional national, state or local codes.
•฀ In Canada, CSA C22.1 Canadian Electrical Code Part
One – latest edition and any local codes.
•฀Wiring must be NEC Class 1 – latest edition. If original
wire as supplied with boiler must be replaced, type 105°C
wire or equivalent must be used. Supply wiring to boiler
and additional control wiring must be 14 gauge or heavier.
•฀Provide electrical ground at boiler as required
by codes.
Thermostat wiring
•฀Install thermostat on inside wall away from influences of
drafts, hot or cold water pipes, lighting fixtures, television,
sun rays or fireplaces.
•฀Follow instructions with thermostat. If it has a heat antici-
pator, set heat anticipator in thermostat to match power
requirements of equipment connected to it. Boiler wiring
diagrams give setting for standard equipment.
Junction box (furnished)
•฀Junction box houses electrical connections for all boiler
components.
•฀Packaged boilers have harnesses furnished.
•฀For Semi-packaged and Knocked-down boilers, trim kits
are furnished with burner and limit harnesses.
•฀All field-provided high voltage wiring must be sheathed in
flexible metal conduit.
•฀Connect incoming line voltage “HOT” wire to service
switch, and neutral wire to white wire. Field-install equip-
ment ground wire to green wire with wire nut.
•฀Service switch (15 amp) is provided with boiler.
For Semi-packaged and Knocked-down boilers —
install switch as shown.
•฀Some local codes may require an emergency shut-
off switch installed at a location away from boiler.
Follow local codes.
Burner wiring
•฀Burner wire harness incorporates a disconnect plug,
providing a convenient way to disconnect wiring
when burner mounting door is opened.
•฀All Packaged boilers have a power disconnect plug
installed on the service switch junction box.
•฀The burner is provided with a burner discon-
nect plug as shown in Figure 20, page 29, or Fig-
ure 23, page 31. For burners in which the disconnect
plug is not factory-wired, connect the threaded
conduit coupling of the disconnect plug wire har-
ness (P/N 591-391-850, included in steam trim
carton) to the burner housing and route the wires
to make all connections in burner junction box as
shown in boiler wiring diagram.
High temperature limit
•฀To comply with ASME, UL 726 or Canadian re-
quirements, an additional high temperature limit
is needed.
•฀Install the secondary control in the supply piping
between boiler and isolation valve.
•฀Set the control to a minimum of 20˚F above the set
point of the combination control.
•฀The maximum allowable set point is 220˚F.
•฀Wire the control as shown on page 28 (float-type
LWCO) or page 30 (probe-type LWCO).