Part Number 000014141 Rev06 9/19 31
Section 2 Installation
Step 5 Leak-Check the Refrigeration
System.
A. Connect power to the ice machine
head section - Do not connect
power to the CVD condensing unit.
B. Press the power switch and
energize the ice machine for 60
seconds to equalize pressures.
C. Disconnect power to the ice
machine head section.
D. Leak-check line set connections, S
trap and all factory joints in head
section and condensing unit.
E. Connect power to the CVD
condensing unit and allow system
to pump down.
Step 6 Insulation Requirements.
To prevent condensation, the entire
suction line, including the shutoff valve,
must be insulated.
All insulation must be airtight and sealed
at both ends.
The following insulation requirements
prevent condensation at 90° F (32°C)
ambient temperature and 90% relative
humidity. If higher humidity is expected,
increase insulation thickness:
Suction
Line
Liquid
Line
Min. Insulation
Thickness
3/4 inch
(19 mm)
1/2 inch
(13 mm)
Suction Line -
1/2" (13 mm)
Liquid Line -
1/4" (7 mm)
5/8 inch
(16 mm)
3/8 inch
(10 mm)
3/4 inch
(19 mm)
5/8 inch
(16 mm)
Suction Line -
3/4" (19 mm)
Liquid Line -
1/4" (7 mm)
Step 7 Insulation for the Suction Shutoff
Valve.
The insulation for the suction shutoff valve
is located in the plastic bag taped to the
water curtain.
Step 8 Ice Beverage Models Only.
The thermostat probe must be moved from
the shipping position to the ice-making
position.
The bin thermostat probe must be
rotated down to enable ice contact and
proper operation.
Verify probe wire does not interfere with
the water curtain.
The control is preset and does not
require programming.
1. Loosen thumbscrew securing probe.
2. Rotate the probe from horizontal to
vertical position.
3. Tighten thumbscrew to secure probe.