Weil-McLain GV90+ Gas Boiler

User Manual - Page 65

For GV90+.

PDF File Manual, 108 pages, Read Online | Download pdf file

GV90+ photo
Loading ...
Loading ...
Loading ...
Part number 550-142-054/1211
65
GV90+ gas-fired water boilerBoiler Manual
Figure 75 Integrated boiler control (IBC) sequence of operation — status light indications
STEPS
(After Step 8, the cycle goes back to Step 1)
Call for
Heat?
POWER TSTAT
CIRC
LIMIT PRESS
SWITCH
FLAME
Timing
1. Standby
• Waiting for call for heat
NO
2. Call for heat
• Circulator on
YES
3. Limit circuit
• Limit controls closed
• Block switch contacts closed
• Blower on
YES
4. Pressure circuit
• Pressure switch contacts closed
• Ignitor glows
YES
30 sec
5. Flame proven
• Gas valve open
• Ignitor remains on
YES
6 sec
6. Limit cycle
• Limit circuit open
• Gas valve closed
• Blower off after postpurge
YES
30 sec
7. Flame outage *
• Flame out
YES
8. Thermostat satised
• Circulator off
• Blower postpurge
• Return to Step 1
NO 30 sec
= ON
= OFF
* If flame is not proven in 4 seconds, boiler recycles 2 times to retry for ignition before going into lockout. Recycle igniter timing
is 30 seconds. Postpurge and prepurge are performed on every cycle. In event of lockout, ignition control will automatically
restore sequence of operation after either:
•1hourwaitingperiod.
•Openingandclosingofthermostatcircuit.
•Removalof120VACpowerforatleast45seconds