Weil-McLain GV90+ Gas Boiler

User Manual - Page 36

For GV90+.

PDF File Manual, 108 pages, Read Online | Download pdf file

GV90+ photo
Loading ...
Loading ...
Loading ...
Part number 550-142-054/1211
GV90+ gas-fired water boilerBoiler Manual
36
Figure 42 Combustion and ventilation air openings for GV90+ Direct Vent installations
The GV90+ boiler CANNOT be in the same space with other appliances if clearances around the GV90+ are less than
the recommended service clearances shown in Figure 2, page 6.
Air openings
The required air opening sizes below are FREE AREA,
after reduction for louver obstruction. Note the ex-
ception below for large spaces.
GV90+ boiler
WITH other
appliances in room
GV90+ boiler
WITHOUT other
appliances in room
TWO openings, each at least:
1 square inch per 1,000 Btuh
of all other appliances in the room
NO openings are required if the
boiler installation provides at least the
recommended service clearances
shown in Figure 2, page 6.
If the space is smaller than Fig-
ure 2, page 6, provide openings
ONLY as shown on page 7 and
Figure 4, page 7.
TWO openings, each at least:
1 square inch per 4,000 Btuh
of all other appliances in the room
— OR —
ONE opening **, each at least:
1 square inch per 3,000 Btuh
of all other appliances in the room
TWO openings, each at least:
1 square inch per 2,000 Btuh
of all other appliances in the room
— OR —
ONE opening **, each at least:
1 square inch per 3,000 Btuh
of all other appliances in the room
TWO openings, each at least:
1 square inch per 4,000 Btuh
of all other appliances in the room
— OR —
ONE opening **, each at least:
1 square inch per 3,000 Btuh
of all other appliances in the room
** NOTICE:
Requirements for using the SINGLE air opening
option.
A single combustion air opening can be used for cases b, c or d above (GV90+ with
other appliances in room only), sized as listed, provided that:
The single opening must communicate directly to the outdoors or to a space that
communicates directly with outdoors (NOT to an interior space).
The top of the opening must be within 12 inches of the ceiling.
The free area of the opening must be at least equal to the sum of the areas of all
equipment vent connectors in the space.
SPECIAL EXCEPTION FOR LARGE SPACES
(GV90+ WITH other appliances in room only):
NO combustion air openings are needed when the boiler (and other appliances) are
installed in a space with a volume NO LESS than 50 cubic feet per 1,000 Btuh of all ap-
pliances in the space. That is, total the input of all appliances in MBH (1,000’s of Btuh),
then multiply this total times 50. The building MUST NOT be of tight construction.
Example: For a total input of 500 MBH (500,000 Btuh), the minimum volume would be
50 x 500 = 25,000 cubic feet (3,125 square feet if ceiling height is 8 feet).
DIRECT VENT — Boiler room air openings
Loading ...
Loading ...
Loading ...