DS-AT1000S Series Storage System Quick Start Guide
6
Construction
The area of the equipment room should meet the
requirements of equipment installation and capacity
expansion. And the ground can bear product loading. The
rooting facilities should be well designed and ready.
Air conditioner
Install an air conditioner which supports power off restart
function in the machine room. The installation position of air
conditioning should ensure no air will blow to the equipment
directly.
Ventilation and heat
dissipation
To guarantee the equipments can be well ventilated, the
distance between the cabinet and the wall shall not be less
than 100 cm, and the distance between two cabinets shall
not be less than 120 cm. It is recommended to reserver 1U
space between two equipments. Ensure aire can effectively
convect between the cabinet and the equipment room.
Dust-free
For the equipment room locating near the dust source (coal
mine, rural road, farmland, etc.), the windows and doors
should be able to keep out the wind and sand.
Transportation
Pack the equipment into the package. Do not transport via
open truck or open warehouse. And do not transport the
equipment with inflammable, explosive, and corrosive goods.
Protect the equipment from rain, dust, and damage.
Particulate pollutant
0.5 μm. Dust in static air should be less than 18,000 in each
litre.
Corrosive gas concentration
The corrosion rate of copper test plate must be lower than
300 Åc in each month. (According to the requirements of G1
level on corrosive gas in ANSId/ISAe-71.04-1985 standard)
Floor bearing capability
Floor load-bearing capability requirement is 600 kg/m
2
. The
height from the floor to the ceiling should be larger than
2.7M. The required load-bearing capacity for the rack is 10 KG
multiply by device chassis size. E.g., a 4U equipment requires
40 KG bearing capability.
Vertical and horizontal
vibration acceleration on floor
surface
When the equipment is halted, acceleration value should not
be larger than 0.5m/S
2.
Grounding
Ensure that each equipment is grounded. Serial grounding is
not allowd. The resistance between the equipment shell and
earth must be less than 4 Ω.
Å is a length unit. 1 Å = 1/10,000,000,000 m