The foundation must be level even
Outdoor unit foundation work
Avoid short circuits and ensure
sufficient space is allowed for service
Installation of outdoor unit
Refer to automatic addressing flowchart
Automatic addressing of indoor unit
In the final check for 24hours at 3.8 MPa(38.7 kgf/cm
2
) there
must be no drop in pressure.
Airtight test
Multiple core cable must not be used.
(suitable cable should be selected)
Electrical work
(connection circuits and drive circuits)
Make sure no gaps are left where
the insulating materials are joined
Heat insulation work
Make sure airflow is sufficient
Duct work
Adjust to downward gradient
Drain pipe work
Special attention to dryness,
cleanness and tightness
Refrigerant piping work
Check model name to
make sure the fitting
is made correctly
Installation of indoor unit
Take account of gradient
of drain piping
Sleeve and insert work
Make connection clearly between outdoor, indoor,
remote controller and option.
Preparation of contract drawings
Indicate clearly who will be responsible for switch setting.
Determination of division work
The vacuum pump used must have a capacity of reaching at least
5 torr, more than 1 hour
Vacuum drying
Recharge correctly as calculated in this manual. and record the
amount of added refrigerant
Additional charge of refrigerant
Make sure there are no gaps left between the facing materials
used on the ceiling
Fit facing panels
Run each indoor unit in turn to make sure the pipe work
has been fitted correctly
Test run adjustment
Explain the use of the system as clearly as possible to your customer and
make sure all relevant documentation is in order
Transfer to customer with explanation
Preheat the crank case with the electrical heater for more than 6 hours.
CAUTION
• The above list indicates the order in which the individual work opera-
tions are normally carried out but this order may be varied where
local conditions warrants such change.
• The thickness of the piping should comply with the relevant local
and national regulations for the designed pressure 3.8MPa(551.1psi).
• Since R410A is a mixed refrigerant, the required additional
refrigerant must be charged in its liquid state.(If the refrigerant is
charged in its gaseous state, its composition changes and the sys-
tem will not work properly.)
!
CAUTION
• Ratio of the connectable Indoor Units to the Outdoor: Within
50 ~ 160%
• Ratio of running Indoor Units to the Outdoor: Within 10 ~ 100%
• A combination operation over 100% cause to reduce each in-
door unit capacity.
!
CAUTION
• The wall thickness of the piping should comply with the relevant
local and national regulations for the designed pressure
3.8MPa(551.1psi).
• Since R410A is a mixed refrigerant, the required additional
refrigerant must be charged in its liquid state.
If the refrigerant is charged in its gaseous state, its composition
changes and the system will not work properly.
• Do not place the refrigerant container under the direct rays of the
sun to prevent it from exploding.
• For high-pressure refrigerant, any unapproved pipe must not be
used.
• Do not heat pipes more than necessary to prevent them from
softening.
• Be careful not to install wrongly to minimize economic loss
because it is expensive in comparison with R22.
!
ALTERNATIVE REFRIGERANT R410A
The refrigerant R410A has the property of higher operating pressure in
comparison with R22.
Therefore, all materials have the characteristics of higher resisting
pressure than R22 ones and this characteristic should be also consid-
ered during the installation.
R410A is an azeotrope of R32 and R125 mixed at 50:50, so the ozone
depletion potential (ODP) of R410A is 0.