16 31-5000579 Rev. 2
ENGLISH
INSTALLATION INSTRUCTIONS
Drain Pipes
Requirements:
• The drainpipe of the indoor unit should be heat-insulated.
Heat insulation should be treated for the connection with the indoor unit. Improper heat insulation may cause
condensing.
Condensate drains must have a pitch greater than 1/100 and have a minimal amount of direction changes or abnormal
noise will be created.
The horizontal run of the condensate line should be less than 66 feet (20 m). Long runs of drain line must be supported
every 5 to 6.5 feet (1.5 ~ 2m) to prevent sags.
• The central piping should be connected according the following drawing.
• Take care not to apply external force on the connection of the drainpipes.
Piping Materials & Heat Insulating Materials:
As avoid condensation, heat insulating material should be
installed. The heat insulating treatment for piping should be
done respectively.
Hose:
The attached hoses can be used to adjust the eccentricity and angle of
the hard PVC tube.
Stretch the hose directly to make connections as to avoid distortion.
The soft end of the hose should be positioned with a clamp.
• The hose should be used in the horizon direction.
Piping Material Hard PVC tube VP 1.2in
(31.5mm) (inner bore)
Heat Insulating Material Vesicant polythene thickness:
over 0.3in (7mm)
3.9in(10cm)(as big as possible)
Down Gradient
over 1/100
VP30
S-shape elbowDown Gradient
over 1/100
Support
Bracket
4.9~6.6ft(1.5~2m)
Heat
Insulating
Material
Hose Clamp
Hose
Indoor Unit
Hose Clamp
Hose
Eccentricity Adjustment (max. 0.8in(20mm))
0.8in(20mm)
45° bending (max.)
45°