9
INSTALLATION
Stacking - 61, 62, 101, 102
STEPS 4-8 ARE FOR GAS OVENS ONLY. For electric ovens, proceed to step “Lift the top oven o the pallet. Place
corrugated cardboard blocks over forks of the lifting mechanism. DO NOT LIFT FROM BOTTOM OF THE OVEN! Be
aware that the oven is heavier on the control side and may tip in that direction. Adjust lift arm position accordingly.”
on page 12.
4. Install ue pipe as follows:
a. Install clamp collar onto ue pipe oven end.
b. Position dense piece of insulation underneath ue pipe as shown in photo.
c. Secure ue pipe to the oven body top with hex head machine screws.
Figure 5
5. Install gas ue pipe cover as follows:
a. Remove the hex head screws from the top body panel
b. Use the screws to attached the ue pipe cover to install the ue pipe cover.
Figure 6